The Yangcheng Lake water diversion project is an important livelihood project constructed to enhance the water supply guarantee capacity of Suzhou City. During the construction process of this project, numerous challenges were also encountered, such as technical difficulties in ultra-long-distance pipe jacking construction and complex geological conditions. However, through continuous innovation and efforts, important phased achievements have been made, providing strong guarantees for the safety of urban water supply.
Project Owner: Suzhou Tap Water Company.
Construction Company: Shanghai Tunnel Engineering Co., Ltd.
Geology: Silty sand.
Engineering Difficulty: Crossing Yangcheng Lake with a single jacking length of 2,600 meters.
Construction time: Stated in September 2019.